Skip to content

Roll Up Performance % Complete

Emma LangMember for 10 years 2 months
Created
1
3
0

I have some activities with zero resources against them. Basically a manufacture line, which I put a % complete against. I would like this to roll up to the summary level. 

Is this possible to do in P6? I've tried changing the % complete type. even using a dummy resource. But it doesn't seem to roll up. 

 

Any suggestions?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    because you can use either

    because you can use either physical % complete, duration % complete or unit % complete to track your % complete you can not roll up certain % completes. This is like mixing apples, oranges and bananas. Try using actviity % complete

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?