P6 Professional R16.2 Resource Unit of Measure Administration

Armando MorilesMember for 8 years 9 months
Created
2
2
0

Hi all,

Using P6 Professional R16.2, I can't find the administration functionality to add a new Resource "Unit of Measure".

Thank you in advance for the help/assistance.

 

Cheers,

Arman

2 replies

Oldest first
  1. 0
    David Kelly ·

    Unit of measure for material

    Unit of measure for material resorces is managed in the Web client if you have an EPPM database. If you have a PPM database, then it isin the admin pull down under categories

  2. 0
    Armando Moriles ·

    Hi David,Thanks for that,

    Hi David,

    Thanks for that, very much appreciated. I did find the Unit of Measure in the EPPM Database under Administer pull down menu, then Enterprise Data. However, it seemed I have no authority to add a new unit of measure. I will just talk to our Administrator.

    Many thanks again.

     

    Regards,

    Arman