Primavera Baseline used bu Acumen Fuse

H MMember for 12 years 9 months
Created
4
3
0

Hi,

 

i'm struggling to undertsnad what baseline Acumen Fuse uses when we export from Primavera. I assumed it will be PROJECT BASELINE but even leaving that field set as Current Project it seems to be picking up a date (that isnt the current finish date).

Can someone explain it in laymans terms for me please.

 

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I would assume that you have

    I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.

    My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified. 

  2. 0
    H M ·

    Hiseems P15.2 doesnt export

    Hi

    seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

  3. 0
    H M ·

    Hiseems P15.2 doesnt export

    Hi

    seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

  4. 0
    Andrew Podolny ·

    Use the Assign Baseline

    Use the Assign Baseline command and select the respective file to be assigned as the Baseline:

    You will see the Symbol B after the Name of your Project in Acumen.

    Regards,

    Andrew