Importing XLS Causing Resource Assignment Duplication
In the Open Standard
Ryan JarreauMember for 8 years 8 months
- Created
- 3
- 2
0
I'm exporting resource assignments from P6 to Excel, updating budgeted units, actual units, and at completion units, then importing and Excel sheet into P6. Once the import is complete, I noticed that the resource has been updated based on my import, and a second resorce has been added and given budgeted units based on units per time that do not match the updated resource. Can anyone give me some insite on what's happening here please? Thanks in advance.
3 replies