It is not unusual for some/many activities to have duration shorter than a whole day, say for example concrete pouring. If you cannot have duration shorter than a work day then why allow scheduling by the hour and minutes? The workaround makes no sense in many scenarios.
Concrete pouring is usually required to be completed within the same work day, if not then shall be scheduled for next available whole day.
Frequently concrete pouring of slabs are allowed to be scheduled to start at earlier time of day and finish latter time of day than other activities.
There is no reason why you cannot have; activities starting at different time of day, activities with remaining durations shorter than a whole day or required to be performed within the same day, the software shall always give the expected start dates.

P6 is notorious for flaws in the calculations of dates and float values under multiple calendars.
PRIMAVERA P6 – FLOAT ON CRITICAL ACTIVITIES?
While it’s quite legitimate to use multiple calendars in any schedule, it can present problems if we attempt to mix those calendars within the logic of the schedule. That is to say activities on one calendar should not be linked to activities on a different calendar if at all possible. Doing so can generate some very perplexing results in not only the dates, but the critical path.
Oracle P6: Critical Path Identification Disorder
One of the most frequently used features of P6 is the capability of using different calendars to schedule different activities of the same project. However, the use of multiple calendars affects the Total Float calculations and accordingly the Critical Path identification.
I have talked to Oracle representatives in several occasions and created Enhancement Requests in Oracle, but unfortunately it seems that Oracle does not have any plans to enhance its P6’s scheduling algorithm in the near future. P6 users should not assume that P6 will always produce a reliable critical path even if the poor scheduling practices are avoided.
P6 -What are critical path activities?
When resource leveling P6 longest path does not works.
The longest path is broken when activities are no longer driven by relationships; that is, when activity dates are driven by constraints or resource leveling.
This seems to be another BUG.