Unable to Import Excel file (.xlsx) in Primavera P6 Professional R16.2.0
In the Open Standard
Shareef Abdul AzeezMember for 21 years
- Created
- 1
- 2
0
I am trying to use a normal export and import function of P6. I exported the data into .xlsx format and I am trying to import the data back after minor edits , but its says "Process did not complete successfully. See log file for details" and the log shows as stated below:
Excel Import log started : 15-Mar-18
INFO: Importing Global Data...
INFO: Importing Project Data...
INFO: Importing:
INFO: Saving:
ERROR: TBOBasedDataManager.InsertNewObject: Cannot resolve foreign key for TASKPRED
ERROR: Failed to find a matching object for Activity Relationship
ERROR: Failed to find a matching object for Activity Relationship
ERROR: Failed to find a matching object for Activity Relationship
ERROR: Failed to find a matching object for Activity Relationship
ERROR: Failed to find a matching object for Activity Relationship
INFO: Saving Data to Database...
INFO: Deleting Unreferenced Data...
Any one has a way around ?
Regards
Shareef Abdul Azeez
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?