Duration % Complete not Rolling Up

Emma LangMember for 10 years 2 months
Created
2
3
0

Hi Everyone, 

Can anyone suggest a reason why duration % complete isn't rolling up to summary level?

My % complete type is the same for all activities, but I'm unsure what else to check

Thanks

Emma

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    The roll up or summarization

    The roll up or summarization uses costs to calcuate the % summary complete. You just cant use duration or how many activies are completed its not weighted but if you assign cost then you have a true weigh value and can calculate % complete because you have a basis to do this just having activities by themselves you have no basis to measure against. 

    if you are looking at the schedule % complete the Summary % complete when displayed on an organize band, will ALWAYS be calculated as Budget Costs for Work Scheduled X 100 divided by Budget at Completion or (BCWS * 100) / BAC, regardless of what earned value technique is selected for the activity's WBS.

    The performance % complete column the Summary % complete when displayed on an organized band will always be calcuated as Budget Costs of Work Performed X 100 or (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.

     

     

  2. 0
    David Kelly ·

    Emma,Duration % complete does

    Emma,

    Duration % complete does role up.

    Activity % complete does not role up, even if all of your % complete types are Duration.

     

     