Changing the order of activities

Charlotte UnderhillMember for 10 years 3 months
Created
5
2
0

Hi All,

I'm new to using primavera, i currently use Asta Powerproject, so this software is scary compared to what i know.

Can anyone help me, i'm trying to simply re-order my activities?

 To explain what i've done so far:

I have added in 3 activities, given them a name and duration, applied logic to them and sceduled. Now i want to add a new activity inbetween activity 1 & 2?

Thanks in advance,

Charlotte

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    it can be used just like

    it can be used just like excel if you click on the top of ANY column your data will be organized alpha numerically in an ascending  order. If you click it again it will be listed in an alpha numeric descending order

    also under group and sort you can also tell it what oder that you want and can have more than 1. i.e. sort order by 

    start 

     

    activity id

  2. 0
    Ahmed Sho ·

    Hi Charlotte You can add more

    Hi Charlotte You can add more activities to the 3activities you have already just the way you added those 3activities in the first place highlight where you want to add another activity and click on the +sign on the right hand side and your activity will be added. Thanks
  3. 0
    Zoltan Palffy ·

    click on the top of the

    click on the top of the column that you want re-ordered

  4. 0
    Gün Göksu ·

    Try to keep a gap of 10

    Try to keep a gap of 10 (default) between the activity ID's if you intend to sort them by ActID (but you will quickly run out).

    On the long term, consider using activity codes and sort through that.

    You can sort by any column by clicking the column header.

  5. 0
    Zoltan Palffy ·

    think I already said that

    think I already said that 

Log in or join to reply