Logic driven by Early Dates
In the Open Standard
Emma LangMember for 10 years 2 months
- Created
- 5
- 7
0
Is there a setting to change to stop the logic being driven by the early dates? When I complete an activity the next activity then changes depending on what the early date is.
Can this be changed? I need my plan to be driven by actual dates and not early dates.
Thanks
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?