New Primavera EPS can't be created !!!
- Created
- 12
- 4
I deleted the EPS in Primavera 15.1, where primavera accepted to delete all nodes, now I have no records in the EPS, it is completely empty.
How can I create a new one if the add button (+) is not available and Primavera doesn't allow to add any new EPS records?
12 replies
Oldest first- 0SASteven Auld ·
Zoltan,The reply before my
Zoltan,
The reply before my comment:
"Thank you for your reply
.Suppose that I'm the adminstrator what should I do to solve this issue?"
Led me to believe that he has Administrator Access.
When you delete all EPS Codes, the + button to Add Projects is greyed out, but you add the EPS from the Enterprise Menu options.
I had taken it to be a bit of confusion between adding Projects & adding EPS Nodes, as you can delete an EPS Node from the Project Screen, but you cannot add it back in from that screen.
If this is not the case, then apologies for any confusion caused.
Steven
- 0ZPZoltan Palffy ·
The hierarchy is EPS then
The hierarchy is EPS then Projects. The projects are UNDER the EPS
The of the EPS as your whole company and within that company maybe you have different divisions or sectors and with in each division or sector are the actual individual projects
EPS = ..........................MY COMPANY
...Geographical area ................West Coast Divisions
.......Type of Sector .................................Education
...........Individual Project .................................Madison High School
...........Individaul Project .................................Valley High School
.......Sector.................................................Industrial
.............Individaul Project ................................Water Treatment Plant
....Geographical area ..................East Coast Divisions
............Type of Sector .................................Education
.................Induviaul Project ..............................Middletown High School
all additions and deletions are done thru
Enterprise
Enterprise Structure
to be able to do this you need admin super user rights
you have to have project privilege 'Add/Edit/Delete EPS Except Cost/Financials
depending on the version
there are 2 two solutions to allowi the user to see their EPS hierarchy structure, and the ability to create new EPS nodes under their hierarchy
Solition #1 Under Administration, Users select the user and under Project Access tab assign an OBS Responsible Manager assignment.
Solution #2 From Project Security Profile assign the Privilege 'Add/Edit/Delete EPS Except Cost/Financials' to the user's assigned Project Security Profile name.
The The two solutions for allowing the user to 1) see their EPS hierarchy structure, and 2) the ability to create new EPS nodes under their hierarchy is solved by following:
- 0SASteven Auld ·
Zoltan,Agree with everything
Zoltan,
Agree with everything you are saying, with the exception of Deletions of the EPS Nodes.
Whilst EPS Nodes SHOULD be deleted through the Enterprise menu settings, Primavera will allow for these to be deleted from the Projects Screen (although it probably shouldn't).
EPS Nodes are saved in the database in exactly the same way as Projects, except that they have the Project Flag set to No instead of Yes for Projects.
Within the database, if you change this flag from N (EPS) to Y (Project) then refresh the Project Screen, the EPS Code will convert to a Project (although not recommended to do this & can only be done within the database itself and not within the Primavera Software).
If someone with Admin rights accidentally deleted an EPS node from the Project Screen, then the option to add it back in would not be available from this screen, as the EPS can only be added via the Enterprise EPS Menu (as we both stated), as this is the only way to set the Project Flag to the correct value.
It would be better if Primavera did not allow the EPS Nodes to be deleted from the Project Screen, as this also deletes ALL the Projects that are under that EPS Node at the same time, however the software will unfortunately allow this to be done.
Steven