Skip to content

Late Start and Late Finish date issue while importing

Gowhar MirMember for 8 years 5 months
Created
3
2
0

Hi there!

I am currently facing this issue wherein when I import a program into another computer the late start and late finish dates change. So technically my entire float is changing.

Any reasons why it might be so? 

I checked the calendar. It is same for both the projects.

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    1 check the calendar again if

    1 check the calendar again if it is using the default calendar then default calendar on your computer and the compueter where it came from may be different.

    2 Also check the calendar at the bottom where it says to Inherit holidays and exceptions from Global Calendar that the correct one is choosen.

    3. make sure that the data date DATE and TIME are the same

    4. in the calculations options make sure they are using the same way when calculating successor relationships

  2. 0
    Gowhar Mir ·

    Thanks, Zoltan. I checked the

    Thanks, Zoltan. I checked the calendars and there laid the problem, holidays weren't assigned in default calendar of one computer. 

  3. 0
    Zoltan Palffy ·

    just as I suspected glad that

    just as I suspected glad that I could help 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?