Performance % Complete Change After Assigning Baseline

Ahmad AbdRabouMember for 11 years 4 months
Created
8
7
0

I've Oracle Primavera P6 Professional R16.2

Project WBS contains 10 Major Items (Sites)

Contractor send update, I assign Baseline for compare Schd % against Perf %

the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !

the remaining sites and the overall Perf % is the same, no changes, has no problem.

I need to know what happened.

8 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I would expect the

    I would expect the performance % complete to changed based on what work got done or did not get done. Why would it stay the same that means that you did nothing

  2. 0
    Ahmad AbdRabou ·

    the problem is, one of the

    the problem is, one of the sites' Performance % Complete Changes after I assign the Baseline, Only one !

    for example:

    Performance % Complete before assinging baseline is 37.67%

    Performance % Complete after assinging baseline is 37.75%

    do you know what happened?

  3. 0
    Zoltan Palffy ·

    has to be something different

    has to be something different ins the schedule

  4. 0
    Ahmad AbdRabou ·

    Can you Explain more so that

    Can you Explain more so that I can test it.

  5. 0
    Zoltan Palffy ·

    a baseline is the planned %

    a baseline is the planned % and NEVER chnages

    the current schedule % complete will change based on progress

  6. 0
    Ahmad AbdRabou ·

    I'll explain the problem in

    I'll explain the problem in other words,

    the contractor submitted an update

    I loaded the udpate and checked for current progress %, it's 37.67%

    then I loaded the baseline and checked the current progress % again to find that it's changed to 37.75%

    what is the reason for that.

  7. 0
    Waheed Elbeih ·

    Hi Ahmad AbdRabouI faced the

    Hi Ahmad AbdRabou

    I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites 

    the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units 

    to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the

    project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the 

    baseline 

    EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline

     

    Regards

    Waheed ELbeih

  8. 0
    Waheed Elbeih ·

    Hi Ahmad AbdRabouI faced the

    Hi Ahmad AbdRabou

    I faced the same problem and this is due to Splitting Activites and resitribution of the Units between the Splitted activites 

    the Problem also occurs when you change the Baseline buget units compared to the updated budgeted units 

    to overcome this problem go to the EPS and select the project and then go to settings TAB and in the project settings use the

    project for calculating the Earned Value is the PRIMAY'S BASELINE and hence, no such change shall be when assigning the 

    baseline 

    EPS>>>>ٍSelect Project >>>>ٍSettings>>>>ٍ User's Primay Baseline

     

    Regards

    Waheed ELbeih

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?