Problem installing Oracle Primavera P6 R 8.2

Raul SantosMember for 16 years 11 months
Created
1
2
0
Hello everyone,
 
I'm trying to install a standalone version of Oracle Primavera P6 R 8.2 on a computer that has Windows 8.1. I have already installed Java (Java 6 update 27), OracleXE and P6. Now, I'm trying to run the "dbsetup.bat" batch file to connect the software to the database, but the Command Prompt window pops up and I get the following error message:  
 
JAVA_HOME IS NOT SET
Press any key to continue ...
 
Does anyone know what is the problem or what I might be doing wrong?
 
Thanks in advance for your support.

1 reply

Oldest first
  1. 0
    Gün Göksu ·

    Hi Raul,Your Java Home is not

    Hi Raul,

    Your Java Home is not set. not found in path.

    To set JAVA_HOME:

    1. Right click My Computer and select Properties (system properties).

    2. On the Advanced tab, select Environment Variables, and then edit JAVA_HOME to point to where the JDK software is located, for example, C:\Program Files\Java\jdk1.6.0_02.

    a logoff/logon, or reboot should then do it.

    I hope this helps.

     

    Searched for "JAVA_HOME IS NOT SET" in google. clicked first search result.