Merging Activities to retain logic
- Created
- 3
- 4
Hello,
I would like to merge a repeating sequence of activities so that a single activity would have the predecessor and successor logic of the five constituent activities. I am not concerned about retaining any conflicting activity code, WBS, calendar, or resource assignments. The purpose is purely to consolidate 5 concurrent activities that make up each cycle of work, but retain predecessor and successor logic.
I figure I can keep the predecessor logic by inserting a new activitity, tying the five component activities to it, then dissolving them. But I can't figure out how to get the various successors of all the component activities into the single activity, other than to do it manually.
Any thoughts are appreciated!
Thanks, Greg.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?