Progressing multiple activities

Floris GeringMember for 12 years 2 months
Created
2
2
0

What is the easiest way to progress a large number of activities in one go ?

(for example progressing all erect scaffolding work to 100% in the pre-shutdown phase of a turnaround)

I am familiar how it works to progress one activity, but manually clicking through 50 scaffolding activities is preferrably not the way to go.

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you can do it 2 ways option

    you can do it 2 ways 

    option #1 export to excel and thne populate then import to p6

    option #2

    filter for all of the scaffolding activites and select 

    tools Update progress then select Selected activities only

    the problem that you have with doing it this way is that it assumes that all of the scaffolding in this filter started and completed on schedule (that NEVER happens)

  2. 0
    Steven Auld ·

    I would agree with Zoltan's

    I would agree with Zoltan's last comment! It is unlikely that they were all started & completed exactly as per plan.

    For only 50 activities, I would just update manually so that you can update the start & finish dates / times as required.

    Depending on the size of the Turnaround & the level of detail in the plan, it is likely that you will need to update more than this most days & they will not all be the same trades so not as easy to filter.

    How you capture progress during the Turnaround is critical in how long this takes to complete each day, so worth spending time getting this right before the Turnaround starts.

Log in or join to reply