P6 not printing gantt chart along with table

David CraigMember for 8 years 3 months
Created
1
5
0

Hi Guys,

 

Have any of you had an issue with gantt charts not showing up on page layout and prints?

 

I can't see gantt charts on the page layout any more. Im not aware of any changes I have made that may have caused this change.

 

I have tried going to Page Setup - Options - Toggled the Gantt Chart button on then off but this doesnt seem to work either.

 

This is become very frustrating now.

 

Any help will be greatly appreciated.

 

Kind Regards,

 

David

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    change setup default printer

    change setup default printer to Adobe pdf in the windows settings

Log in or join to reply