Hi mates. I am working on 18 hours calender, 2 Shifts (9hrs X2). I have been asked to use 10 riggers over all. So what would be our maximum units per time and default units per time.

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    But at times the crew

    But at times the crew composition of different shifts working on same activity is different, also it might also be desirable for shifts to have some overlap.  Easy if modeling different teams working independent of each other [at different hours] on same activity. 

    2_Shifts10_Riggers

    It is Volume of Work and Productivity [production rates ] what gives meaning to activity durations.

    Riggers_Volume_Of_Work

    If start of activity is delayed for latter on same day the work done by the different shifts is re-distributed and activity duration changes, therfore it is not a good idea to split the activity into two. 

    SW0023

    To make is easier to visualize say: 

    • Crew 1 shift 1 works on Monday, Tuesday, Wednesday and can do 50% of work per day.
    • Crew 2 shift 2 works on Thursdays and Fridays and can do 100% of work per day.  
    • Easier, no overlapping, shift work on different days .
    • If activity stars on Monday it will take 2 days, if activity is delayed to start on Thursday it will take one day.

  2. 0
    Zoltan Palffy ·

    either 5 or 10 depeneding on

    either 5 or 10 depeneding on how you set up your calendars and shifts 