Resource Shifts
In the Open Standard
Adab AzeezMember for 10 years 3 months
- Created
- 5
- 2
0
Greetings to everyone.
I am creating a 24 hour Shutdown schedule.Now I Resources are being assigned. There are two working shiftsin this Shutdown first shift- 7Am to 7pm and second shift 7Pm to 7 am.
My question is Is it necessary to create two shifts for each resource, when the price per unit is same?
May be, I would be asked to put 12 manpower in day and 8 in night so how to assign resource in this case ? Can anyone guide please ? Regretfully I am not good when it comes to use resources in P6.
Thank you to everyone.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?