BL Duration % Complete
In the Open Standard
Gowhar MirMember for 8 years 5 months
- Created
- 3
- 1
0
Hi there!
I require to show the project progress in terms of duration % complete but the issue is that the assigned baseline duration % complete doesn't auto update. I now am updating actuals on baseline seperately to get the data. Is there a way wherein I can represent both the baseline Duration % complete and current duration % complete together in the same prog?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
