just so that I understand you included the planned monthly anticipated adverse weather days by month into your calendar. Lets say that for this example we wil use the month of August. So the the planned adverse weather days during the month of August were anticipated to be 5 days. You actually experienced 6 days of adverse weather to activites that were on the critical path. This means that 6 actual adverse - 5 planned adverse = 1 day that you are owed as a non compensable time extension.
The answer to this question depened on how or if you have already updated your schedule for the month that you experienced the 1 day of adverse weather above the normal anticipated adverse weather.
There are several ways to do this.
Schedule already updated through August
If you have already updated the schedule through the month of August means that in effect you have already captured this delay becasue lets say a 5 day activity on the critical path actually took you 6 days to do becasue the 1 extra day of weather. This would be reflected in the actual start and finish dates.
change the project must finish or the project milestone finish on or before date by 1 day and modify the milestone activity name and add "REVISED to dd/mm/yy based on adverse weather during August.
Schedule NOT updated through August
Option #1 add a 1 day activity and insert it as a SUCCESSOR to the project completion milestone and call it Adverse weather during August 2018 and then add a New Milestone call it revised project completion based on adverse weather.
Option #2 add a 1 day activity and insert it as a predecessor to the project completion milestone cal it adverse weather during August. Make sure to connect its predcessor an activity that is driving and critcal.
Option #3 add a 1 day activity and insert it as a SUCCESSOR to the activity that it actually happened to. for example if it was excavation then insert a new 1 day activity called adverse weather during August. Make its predcessor the excavation activity and make its successor whatever the successor to the excavation was. The problem with this method is that is is sort of Planning and actualizing weather all in the same update.
points to remember
- whatever you do make sure to change the project must finish by date if you are using it and or the last activity mielstone finish on or before date by 1 day.
- if inserting a NEW activity make sure that the predcessor and successor is driving and critical.
- Use the notebook function to document what you have done and why you have done it.