New to Delay Analysis—Seeking Immediate Guidance, Please

Md Sakib IslamMember for 11 years 1 month
Created
4
5
0

Greetings to everyone

Hi

I am currently working on a delay analysis, and to be very honest, this is my first time tackling such a task. I am feeling quite stuck and could really need some help. I would be incredibly grateful if anyone could offer me some advice or pointers.
Here in UAE, we noticed a delay, during Ramadan time.our time has reduced from 8 hours a day to 6 hours a day. but we were getting work permit only for 3 hours a day.
So how can I estimate in Primavera that which activity is getting affected by this and by how much duration it is getting affected. Please help.

4 replies

Oldest first
  1. 0
    David Kelly ·

    Take a baseline.Annotate all

    Take a baseline.

    Annotate all of the activities, perhaps with a code value, that have had their working day reduced to 3 hours

    Run a Global Change, which alters the calendar of those activities to three hours per day

    Reschedule

    Baseline reports will show deviations cuased by the reduction of working hours

  2. 0
    David Kelly ·

    Take a baseline.Annotate all

    Take a baseline.

    Annotate all of the activities, perhaps with a code value, that have had their working day reduced to 3 hours

    Run a Global Change, which alters the calendar of those activities to three hours per day

    Reschedule

    Baseline reports will show deviations cuased by the reduction of working hours

  3. 0
    Renzo Constenla Bravo ·

    Hello the solution is that

    Hello

     

    the solution is that mentioned by Mr. Kelly.

    Just to indicate that this problematic (time deviation, delay analysis, extension of time, etc) related to  forensic analysis is very interesting in planning/scheduling. There are several approaches to time impact analysis. Try with AACE recommended practices (among others).

    Regards

  4. 0
    Zoltan Palffy ·

    get your hands on the 52R-06

    get your hands on the 52R-06 Time impact alanysis - as applied in construction 

    this is a best practiice material that shows you how to do it 

    this is by the aace which is the Association for the Advancement of Cost Engineering

     