Inter-project links
- Created
- 3
- 3
Hello folks,
This in regards to my effort to carry a summary level schedule (about ~ 250 lines), out of 10000 line itmes schedule, to provide the management, overall high-level view of the project. The big part of the 10000 line items is EPCM schedule, which gets updated monthly. The way I created it, I used summary LOE activities in summary schedule and linked ss and ff with 10000 lne item schedule. However, when I update it on monthly basis and re-schedule, I start getting circular relationship issue and I can not update the ISS file. I was wondering help on 2 things:
What might be the issue that seems to causing the circular relationship &
Is there a better way to manage standalone integrated summary schedule
Many thanks in advance for your help.
Younus
3 replies
Oldest firstLog in or join to reply