Change Duration when adding extra Resource
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 4
- 2
0
Hi All,
What settings must I use to get P6 to change Activity Duration when I add extra Resources?
Lets say I have I have a 10 day activity with 1 Resource on it and 100 units, when I add an additional same Resource I want the duration to reduce to 5 days and retaining 100 units.
Thanks,
Rod
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?