Change Duration when adding extra Resource

Rodney JonesMember for 14 years 4 months
Created
4
2
0

Hi All,

What settings must I use to get P6 to change Activity Duration when I add extra Resources?

Lets say I have I have a 10 day activity with 1 Resource on it and 100 units, when I add an additional same Resource I want the duration to reduce to 5 days and retaining 100 units.

Thanks,

Rod

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you can change the duration

    you can change the duration TYPE to fixed units. As you change the units this will change the duration. 

    you can also change the activity type to resource dependent. This will use the resource calendar as opposed to the activity calendar. You usually use this if you have multiple resouces on the same activity. 

  2. 0
    Alexandre Faulx-Briole ·

    Hello guys,do not forget to

    Hello guys,

    do not forget to change the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...

    this way, P6 will split the 100 hours assigned to Resource #1 between the original and the additional resources

    Alexandre

  3. 0
    Rodney Jones ·

    YES! the User Preferences,

    YES! the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...

     

    that was the setting I couldn't remember, thanks Alexandre.

  4. 0
    Rodney Jones ·

    How do I close this

    How do I close this post?

     

    Admin,, please mark this post as Solved.