Hi Guys,

Just like to know why is there a gap in updating or progressing on an activity on on-going projects? Also is there a way to mitigate this?

Another, can you guy provide reference guide in making or doing an Delay Impact Schedule?

Thanks in Advance.

Cheer!

Ruel

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    select bar and for the actual

    select bar and for the actual work bar select Current Bar as the timescale ist the 3rd column from he left under Bars.

    for Delat Impact look at At AACE Recommended Practice No. 52R-06 Time Impact Analysis 

  2. 0
    Ruel Camaquin ·

    Thanks Zoltan! You been a

    Thanks Zoltan! You been a great help to the Primavera P6 Community.

  3. 0
    Zoltan Palffy ·

    I do what I can

    I do what I can