While updating progress of my Project schedule, I am getting some values of unit% complete and physical % complete against certain value of schedule % complete, with each scheduling BUT.. why I am not getting performance % complete? Performance % complete is always zero which I am not expecting. My duration type is Fixed duration and unit per time. % complete type is duration. Resources have certain prices and values. Any help please ?

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you have to use physical %

    you have to use physical % complete

  2. 0
    Adab Azeez ·

    But in some of my project I

    But in some of my project I am getting performance %. Literally I tried a lot but not able to understand the ligic behind this usage. Thanks anyways.
  3. 0
    Kannan CP ·

    Hi,For the performance %, you

    Hi,

    For the performance %, you have to assign cost (as a weight factor or as per BOQ) in order to calculate the earned value.

    BR

    Kannan