Detailed Resource allocation after Export and then Import
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 13
- 4
0
Hello Everyone,
Need some help. Can we Export Activity to Excel and then populate the resorce in it and import it back to P6. And that too if the same activity has multiple resource like,
Activity - Foundation for Tank
Resource:
Steel Fixer - 40 Hrs
Carpenter - 16 Hrs
Mason - 16 Hrs
Labor - 112 Hrs
I would like to see in the imported Excel something like this so that it easy to load the resource,
| Activity ID | Activity | Steel Fixer | Carpenter | Mason | Labor |
| A-1000 | Foundation for Tank | 40 | 16 | 16 | 112 |
Thanks
Jithin
13 replies
Oldest firstLog in or join to reply