Skip to content

Detailed Resource allocation after Export and then Import

Jithin KambhikanamMember for 15 years 6 months
Created
13
4
0

Hello Everyone,

 

Need some help. Can we Export Activity to Excel and then populate the resorce in it and import it back to P6. And that too if the same activity has multiple resource like,

 

Activity - Foundation for Tank

Resource:

Steel Fixer - 40 Hrs

Carpenter - 16 Hrs

Mason - 16 Hrs

Labor - 112 Hrs

I would like to see in the imported Excel something like this so that it easy to load the resource,

Activity IDActivitySteel FixerCarpenterMasonLabor
A-1000Foundation for Tank401616112

 

Thanks

Jithin

13 replies

Oldest first
  1. 0
    David Kelly ·

    Jithin,Yes you can export a

    Jithin,

    Yes you can export a template of resource assignments, and import them with new values BUT it cannot be done in the format you want.

     

    It must be one row in the spreadsheet, one resource assignment:

    A-1000  Steelfixer 40

    A-1000 Carpenter 16

    A-1000 Mason 16

     

    etc.

  2. 0
    Jithin Kambhikanam ·

    Hi David, Thanks, could you

    Hi David,

     

    Thanks, could you guide me with an example like how the template would be in actual. I am in Oil and Gas same as you, so my current scenario for example there is a deliverable Design Basis for which all the Dicipline needs to give there input so that 1 Deliverable would have hours of Process, Mechanical, Piping, Electrical, Instrumentation, Civil. So I need to put hours of all of this dicipline into to this Delvierable as a separate resource.

     

    I will be working on a Project in which there would be many engineering deliverable.

     

    So could you help me out with an example

     

    Regards

    Jithin

  3. 0
    Santosh Bhat ·

    Just manually populate one

    Just manually populate one activity with the resources and units you want to include.

    Then select FILE>EXPORT>XLS>RESOURCE ASSIGNMENTS and it will be easy to see how this is done

    Then complete populating in Excel and select FILE>IMPORT>XLS and point to the same file exported above.

  4. 0
    Jithin Kambhikanam ·

    Hi Santosh, Ya did that and

    Hi Santosh,

     

    Ya did that and Yes it showing but in a Horizontal Way. Like if for 1 Activity if there is 10 Resource then the 10 Resource would be shown Vertically. 

     

    But before it is been exported under the Template, in the Subject Area you have to select Resource Assigment and add the related columnn

     

    If the resource was shown Horizontally per Activty then the Resource loading would have been better.

     

    Thanks

    Regards

  5. 0
    Kannan CP ·

    Hi Jithin,I believe that

    Hi Jithin,

    I believe that after the exporting, you can't change the basic structure of the excel file ( top-down to horizontal).

    You can filter the act-ID and populate the resource units much faster in the excel file, and then you can import it.

    BR

    Kannan

  6. 0
    Santosh Bhat ·

    Jithin,The XLS import/export

    Jithin,

    The XLS import/export work as the Database tables are written, to have one line per activity with all the resoures horiztonally would not be a flat data file.

    You could develop some excel forumals using INDEX and VLOOKUP formulas to achieve what you're after.

  7. 0
    Jithin Kambhikanam ·

    Hi Kannan, I stared doing

    Hi Kannan,

     

    I stared doing that. Filter it by Activity ID then populate.

     

    Ya that is one more Idea, let me see which would be faster and better.

     

    Regards

    Jithin

  8. 0
    Kirill PM ·

    I think you are looking for

    I think you are looking for something like this:

    https://youtu.be/6_KZYCOBl-k

  9. 0
    Santosh Bhat ·

    Kirill, Thats an interesting

    Kirill,

     

    Thats an interesting application - but seems to be only available for the Russian market? Is there any infromation availabel in English - other than a website auto-translation?

  10. 0
    Kirill PM ·

    Unfortunately there are no

    Unfortunately there are no materials in English for now.

    We are in the process of creating a new website, the English version will be ready in a month i think.

  11. 0
    Kirill PM ·

    Unfortunately there are no

    Unfortunately there are no materials in English for now.

    We are in the process of creating a new website, the English version will be ready in a month i think.

  12. 0
    Santosh Bhat ·

    Kirill,  Thank you, I look

    Kirill, 

     

    Thank you, I look forward to seeing more about it.

  13. 0
    Zoltan Palffy ·

    assign the resources to the

    assign the resources to the activities in p6 then export to excel then populate then import to p6

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?