Filtering activities

Arawinda NawagamuwaMember for 7 years 9 months
Created
5
1
0

Hi,

In our project plan, I want to filter acitivities under Podium - Level 01 (Activties circled in attached image). Please help.

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I am assuming that these

    I am assuming that these activites have been assigned a wbs and not codes.

    Therefore filter where wbs is under Poduim Level 1

  2. 0
    Santosh Bhat ·

    Use Activity Codes, much more

  3. 0
    Zoltan Palffy ·

    codes will work also and are

    codes will work also and are much more flexible than using a wbs 

  4. 0
    Arawinda Nawagamuwa ·

    Dear Bros.... Thanks all...I

    Dear Bros.... Thanks all...

    I used filtering by activity codes and it worked.

    Thanks again for your support.

  5. 0
    Zoltan Palffy ·

    glad we could help

    glad we could help 