Remaining Duration - Update Automatically?
In the Open Standard
Emma LangMember for 10 years 2 months
- Created
- 1
- 3
0
Is there a setting so the Remaining duration updates automatically for activities which are in progress.
I.e. for a 10 day duration with an actual duration of 5 days then the remaining would be calculated to 5 days?
I currently have a 64 day activity, when I schedule it a a few weeks later than the start the remaining duration is still 64 days. It is set to Physical % Complete, at 95% complete.
I've tried to change lots of different settings in the project window, user preferences, schedule options etc.
Any help would be appreciated.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?