Remaining Duration - Update Automatically?

Emma LangMember for 10 years 2 months
Created
1
3
0

Is there a setting so the Remaining duration updates automatically for activities which are in progress. 

I.e. for a 10 day duration with an actual duration of 5 days then the remaining would be calculated to 5 days?

I currently have a 64 day activity, when I schedule it a a few weeks later than the start the remaining duration is still 64 days. It is set to Physical % Complete, at 95% complete. 

I've tried to change lots of different settings in the project window, user preferences, schedule options etc. 

Any help would be appreciated. 

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    what you can is to run a

    what you can is to run a global change to make the duration % complete equal to the physcial % complete

    go to tool global change 

    New

    where Percent Complete Type equals Physical 

    then duration % complete = Physical % complete

    now on the rigth select Change

    then on the botton right select Commit Changes