Skip to content

LoE budgeted units not matching activity calendar

Dan PittsMember for 14 years 10 months
Created
2
2
0

I have a role assigned to a LoE (fixed duration & units/time) which has a standard 5 day calandar.

Budgeted units / time is 100% and the total budgeted units in the resource assignments window match the activity duration. Planned dates match forecasted.

 

The issue is that in the resource assignments spreadsheet it is showing 25 units in June 2019 where the calendar only has 20 working days. Why are the budgeted units not aligned to the activities calendar?

2 replies

Oldest first
  1. 0
    Dan Pitts ·

    Hmm... have just restarted

    Hmm... have just restarted Primavera and all appears to be displaying as expected in the resource spreadsheet. Weird!

  2. 0
    Zoltan Palffy ·

    if you assign a budget to a

    if you assign a budget to a LOE activity type you MUST assign a resource CURE or the units will all stuck up on the data date.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?