Lag and Original Duration

Larry CahnMember for 8 years 10 months
Created
3
1
0

I need to have an excel spreadsheet that lists all activities original duraion as well as lags.

I've tried numerous was of P6 exporting to excel, filtering/formatting within P6 to copy and paste in excel, but am unable to find a way to get both the original durations and lags on one spreadsheet.

Does anyone have any ideas? Thanks!

3 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi LarryYou can use the

    Hi Larry

    You can use the 'Reports' feature for all the relationships in the schedule. Also the lags.

    Go to Tools < reports and then select report AD-02 activity relationships.

    Regards Johannes

  2. 0
    Santosh Bhat ·

    Open the projectSelect

    1. Open the project
    2. Select FILE>EXPORT>XLS
    3. Select both Activities and Activity Relationships
    4. The default Export template should be sufficient for what you need
    5. Select a locaiton to export the XLS file to
    6. Open the XLS file
    7. There is one tab for the activity infomration where you'll find duraton
    8. There is a second tab that lists all Relationships inlcuding lags
    9. Use VLOOUP to match the predecessor ID in the relationships tab to the duration in the activity tab
  3. 0
    Zoltan Palffy ·

    Santosh has the solution

    Santosh has the solution

Log in or join to reply