Skip to content

Remaining Units not calculating - why?

Gavin MacLeodMember for 15 years 7 months
Created
1
3
0

Hi,

I'm back using P6 after a few years off and have been tasked with creating a resource histogram that shows the remaining hours.

Each time I run the report it is showing me the remaining actual units and not the remaining to earn.

eg.

Budget = 240, % Comp = 95%, Actuals = 210, Earned = 228

When I run the report it should tell me I have 12 hrs left remaining, however it says I have 30 hrs left.

I have my activities set up as Task Dependant, Fixed Duration & Units & Physical % Complete.

Any ideas?

 

Many thanks,

Gavin

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    are you updating remaining

    are you updating remaining duration ?

    what calculation are you using for earned value  ?

    this is under

    Admin Preferences

    then the Earned Value Tab.

    Technique for  computing Estimate to Compete (ETC) 

    and  at the bottom Earned value calculation should be Earned value with current dates

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?