Global change not working for baseline programme

Kevin RaynerMember for 17 years 9 months
Created
2
3
0

I am aware of the need to change the planned start and planned finish of a baseline programme before attaching it to the programme that I am usuing to demonstrate a delay.

However in certain instances the planned dates are not being changed. ie an activity in progress with and actual start of the 30 May 2018 and a finish of the 3 Dec 2018 after running the global change to set the planned dates gives a planned start of the 30 May 2018 but a finish of the 30 Nov 2018 and not the 3 Dec 2018.

I assume that the global change is:

Condition 1 activity complete. planned start=actual start planned finish=actual finish

Condtion 2 activity in progress. planned start=actual start planned finish=finish

Is this correct?

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    how come you are mixing

    how come you are mixing planned start date with finish dates  ?

    actual start = planned start

    actual finish = planned finish

  2. 0
    Kevin Rayner ·

    You are aware that when

    You are aware that when comparing a programme with an attached baseline it is comparing the planned dates of the baseline?

Log in or join to reply