BL Budget At Completion and PV is Not Matching At Completion Total Cost for a Completed Activity

Ali AljaberiMember for 7 years 5 months
Created
1
2
0

Hi,

I have an activity in my schedule that has a Budget At Completion=PV=EV=$16,451.87, while my At Completion Total Cost for that activity= $66,084.98 (as in the attached screenshot).

The Baseline was snapped two months after the activity finish date was actualized; I tried to update the BL couple of times for that specific activity, but its still showing No matching values. 

Anyone went through this situation before please?

Thanks.

 

Ali

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    release the baseline fix it

    release the baseline fix it then re-attach it.

Log in or join to reply