Primavera P6 Professional v18.8 Importing XML files failing

Steve MontgomeryMember for 7 years 11 months
Created
2
1
0

Hello,

I recently upgraded to Oracle Primavera Professional version 18.8 and now I am unable to import P6 XML files or Microsoft Project XML files. This happens for both a MSSQL database and SQLite database.

Also, I went to the Oracle website https://edelivery.oracle.com. The latest version of P6 Professional was 18.8 and I did not see a patch fix later than 18.8.0.0.

Any input or guidance would be greatly appreciated.

--Steve

2 replies

Oldest first
  1. 0
    Edison Gabion ·

    Good day Mr. Stevetry to open

    Good day Mr. Steve

    try to open as a note your .xer file and change the version inside of the file and import.

    1. question from where did you brought the v18.8 how much for single user

  2. 0
    Steve Montgomery ·

    I'm trying to import a P6 XML

    I'm trying to import a P6 XML file and not a P6 XER file.