Deleting activities on a baselined plan
In the Open Standard
Emma LangMember for 10 years 2 months
- Created
- 5
- 2
0
Hi, I'm looking for some advice on deleting activities on a plan. I need to delete some activities which are no longer valid and redistribute hours to new activities. The plan has been baselined. What is the best way for me to do this? I'm looking for the best practice.
I've tried deleting activities from both the plan and the baseline before and also dissolving activities. If I'm creating new activities I also need to add these into the baseline? I'd like to know the right way to do this, any ideas or advice would be great.
Thanks
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?

