% Complete calculated from Baseline

Katia PopovaMember for 7 years 4 months
Created
2
2
0

Hi there!

I am fairly new to Primavera, therefore the below question may seem a little strange to some of the pros here.

In the programme update for the client, I've been asked by a colleague to calcualte % complete that we should be on as of Data Date used for the current reporting period. I normally use % Schedule Complete to show the % complete that we should be on now. (I hope this is the right way of doing it!)
If this is the correct way of identify the % Complete we should be as of a specific Data Date, then which Baseline would this be calculated against - Project BL, Primary BL..etc? What if I have few BL assiged, which one will be picked up?

I apprecate your help!

Katia

2 replies

Oldest first
  1. 0
    David Kelly ·

    Katia,SChedule % complete is

    Katia,

    SChedule % complete is correct

    It comes from the baseline copy defined as the "Project" baseline

    SChedule % complete shown on summary (eg WBS) bands are waited BY COST this is very important to understand

  2. 0
    Zoltan Palffy ·

    is your schedule resource

    is your schedule resource loaded ? what are you using as your measuring stick >

Log in or join to reply