Turning a non-resource level schedule into a resource loaded one (P6)

Eric GonzalezMember for 7 years 4 months
Created
1
2
0

I have taken over a schedule that is not resource loaded. However, management would like to add resources even though job has already started. The job is a EPC project. The constuction side is resoure loaded but not the engineering side. What would be the best solution for this task? Would I need to make a copy of the baseline, export, make the changes to include resources then import back in? 

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    add a labor resource export

    add a labor resource 

    export both to excel 

    copy the non labor data values to the labor resource

    import the excel file

    deleted the non labor resource 

    done