Importing a Microsoft Projects with Project Actuals Into P6 to compile a baseline

Eric GonzalezMember for 7 years 4 months
Created
5
4
0

I have been given a project that has actuals in Microsoft Project. I need to pull out the baseline from this into p6. What would be the best solution once inported into p6? Would I need to uncheck the finish and start section on the actuals? There are about 1200 activies and another alternaitve would be helpful. 

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    take it into p6 and destatus

    take it into p6 and destatus the project I sent u an email here I can send instructions on how to de-status

  2. 0
    Zoltan Palffy ·

    take it into p6 and destatus

    take it into p6 and destatus the project I sent u an email here I can send instructions on how to de-status

  3. 0
    Rafael Davila ·

    https://www.planacademy.com/h

    https://www.planacademy.com/how-to-remove-actuals-from-primavera-p6-schedule/

    Please be reminded that - "... there exists a common trend with Microsoft Project users which is quite common across the world. These schedulers simply ignore the requirement for proper planning logic and insert negative lags to achieve a quick programme with minimal activities".   

    https://www.gbaprojects.com.au/uploads/files/whitepaper_-_poor_planning_negative_lag.pdf

    You might need to adjust the logic of MSP schedules. 

  4. 0
    Eric Gonzalez ·

    Thank you all for the useful

    Thank you all for the useful information. I have found how to uncheck start and finish statuses. I initially did a globacl change to correct this. 

  5. 0
    Zoltan Palffy ·

    yes that is correct u have to

    yes that is correct u have to run a couple global changes to de-staus a project and also change the data date 