Same resource - but different pay rates

J RamMember for 7 years 3 months
Created
3
1
0

Hello everyone,

I'm new to this forum as well as new to Primavera P6. My question is regarding assigning different rates for the same resource. So let's say we have a job starting on June 1st, 2019 for an Outside Machinist at a rate of $58 / hour, but we also have the same Outside Machinist working on another job on June 1st, 2019 but at a different rate of $60 / hour. Is there a way to incorporate this onto a schedule to reflect it's budgeted labor cost or is there an alternate way? The reason why I'm trying to do this is because I want to have a Master Schedule that shows all work and the resources assigned, but the same resource works at different rates.

 

Thanks for the help!

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Set the Effective Dates and

    Set the Effective Dates and Time for each Rate in the Units & Prices Tab of the Resources.

  2. 0
    Rafael Davila ·

    https://tensix.com/2015/06/pa

  3. 0
    J Ram ·

    Thank you both the help. I'll

    Thank you both the help. I'll mess with a few things and hopefully this solves what I need.