Resource assignment Importing
In the Open Standard
Shaun ChewMember for 10 years 10 months
- Created
- 5
- 2
0
Hello everyone,
i have an issue when importing resource assignments, if i export an excel file with activities and resource assignment data and adjust the budgeted labour units ln the TASKRSRC tab and then import the excel file the units in p6 will be modified and it works fine. alternatively if i create my own excel file, (not modifying one that has been exported) instead of it modifying the budgeted units it creates an additional resource assignment to the activity and the existing assignment remains the same.
would appreciate any help on this, thanks