Percent Complete Changed when Baseline is inserted

Robin ReyesMember for 20 years
Created
3
4
0

I am receiving an xer for the schedule update from the Contractor. The percent complete used for progress is the Cost Percent Complete. However, when I inserted the baseline into the schedule, the values on the Cost Percent Complete changes. When i removed the baseline, the Cost Percent Complete return to its original values. Does anyone knows the reason behind this? Thanks

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    goto AdminAdmin

    goto 

    Admin

    Admin Preferences

    Earned Value Tab

    Then at the bottom under earned Value Calculations

    make sure that the selection is Budgeted Values with current dates NOT PLANNED DATES

  2. 0
    Johannes Vandenberg ·

    Hello ZoltanThanks for this

    Hello Zoltan

    Thanks for this information. I recently moved to a new P6 database and forgot to change this default setting. Cost me hours to correct. Paul Harris also published this particular setting in the Admin.

    Regards Johannes

  3. 0
    Zoltan Palffy ·

    just ask here or in linkedin

    just ask here or in linkedin and we will set you strainght.