Error while converting from Primavera P6 R15.2 to XML Microsoft project format

Mehdi RideneMember for 7 years 8 months
Created
4
5
0

 I have an error when I try to convert from Primavera P6 R15.2 to XML Microsoft project format. ( see error screenshot)

 

Please advise me with appropriate solution. Thanks

  

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    please click on the log file

    please click on the log file so that we can see the error ?

    We can not figure out the error just from this. 

    This is like going to the doctor and saying I am sick without telling the doctor whats wrong with you. 

    need more detail. 

  2. 0
    Santosh Bhat ·

    Tips on using this forum..(1)

    Tips on using this forum..

    (1) Explain your problem, don't simply post "This isn't working".

  3. 0
    Mehdi Ridene ·

    Hallo, I changed the Java

    Hallo,

     

    I changed the Java version and it is working again. The issue starts when I migrate to windows 10.

     

    Thank you

  4. 0
    Zoltan Palffy ·

    tunr off the automatic

    tunr off the automatic updating of the java version in your control panel so that this does not happen again