Actuals remain at zero when activity started and a perecnt complete applied.
In the Open Standard
David BallMember for 19 years 2 months
- Created
- 3
- 2
0
Hi,
When an activity is Started and a Physical % applied (eg 80%), I F9, and the Actual Labor Units remain at zero.
When I look in the Resources tab of the Activity Details window the Units % Complete is also zero. If I manually adjust the Units % Complete the Actual Labor Units then adjust correctly.
My settings are:
Act Type: Task Dependent
Dur Type: Fixed Duration & Units
% Complete Type: Physical
What other settings would be likely tyo be causing this problem?
Thanks very much
Dave
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?