Doubt P6 - At Complete versus BL Project

Helder RodriguesMember for 7 years 1 month
Created
5
4
0

Hello,

I have a doubt:

Schedule "A" has an At Complete of 7.94% in July / 19 before being entered as the baseline for Schedule "B".
Its Ok for me...
But after schedule "A" is entered as baseline on schedule "B" the field "Cum BL Project Nonlabor Units" has a% of 7.61%
What am I doing wrong?
 

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    go toAdmin Admin

    go to

    Admin 

    Admin Preferences

    go to the Earned Value tab 

    at the bottom where it says Earned Value Calculation When calculating value form a baseline use

    change this to Budgeted value with current dates or At completion values with current dates 

  2. 0
    Helder Rodrigues ·

    Hello Zoltan, I don't have

    Hello Zoltan, 

    I don't have access to Admin menu
     
    Is there another solution to this problem?
     
     
    Regards,
  3. 0
    Helder Rodrigues ·

    Hello Zoltan,  I don't have

    Hello Zoltan, 

     

    I don't have access to Admin menu 

     

    Is there another solution to this problem?  Regards,

  4. 0
    Raymund de Laza ·

    Suggests to Set the Planned

    Suggests to Set the Planned Dates equal to Current Dates.

  5. 0
    Zoltan Palffy ·

    then get access to it or talk

    then get access to it or talk to the adminstrative person who does have rigths to this