Activity ID Number Renumbering
In the Open Standard
Muhammad SaqibMember for 7 years 11 months
- Created
- 2
- 2
0
Dear All,
I have completed the schedule and i have added so many additional activities who has differenet Activity number.
Started with A1000 and Ends with A11506 etc.
Now i want to Renumber the Activity ID with same activities sequence displayed. I followed this Youtube method (https://www.youtube.com/watch?v=S1ynA1wRwuc) and it works on small project but not in my current project. I mean it renumbered the ID but sequence is wrong. Activities ID is spreading in all other categories.
2 replies