Skip to content

Primavera P6, 16.1: Progress line on collapsed group activities

Jon GustoMember for 7 years
Created
2
2
0

Hi,

 

Is there any way to make progress lines track the grouping of collappsed activities. I have late start activities and it tracks the individual activities and milestones but if I collapse them in group lets say grouped in Level 1, the progress line doesnt track the delays.

 

2 replies

Oldest first
  1. 0
    Baykan Yigit Sogut ·

    Progress line functions only

    Progress line functions only in activity level. Primavera doesnot recognize the Summary bars as activity and doesnot do any plan/actual calculation.

  2. 0
    Zoltan Palffy ·

    no and why would you want to

    no and why would you want to do that anyway ? 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?