Excel spread sheet to read XER files

Ron BeecheyMember for 10 years 6 months
Created
5
1
0

Looking for excel spread sheets or the likes to read xer files and produce curves and any other helpful information.   I have one "01-XER-READER" which I found very good but wondered if there was a actual curve that could be added.  There may be also an update which I have not been able to find.   Always good to not reinvent the wheel if someone has already worked on something.

5 replies

Oldest first
  1. 0
    David Kelly ·

    Project Tracker does

    Project Tracker does everything for a couple of hundred pounds. Even reads the database directly so you can produce real "S" curves without creating a second data source.

  2. 0
    Bryc Ali ·

    How we can read the data base

    How we can read the data base directly to produce S curve ?

  3. 0
    David Kelly ·

    Bryc, Easy. Use Project

    Bryc,

     

    Easy. Use Project Tracker.  Reads the database, lets you take baselines, makes "s" curves with the data range table underneath.

  4. 0
    Zoltan Palffy ·

    yes project tracker can do

    yes project tracker can do that 

  5. 0
    Joel Roberts ·

    Hi Ron.You can use

    Hi Ron.

    You can use ScheduleReader to read XER, XML or XLS files.

    You can see S-Curves, Histograms, compare baselines, trace predecessors and succesors, filter, group, sort through data and even create reports from the data inside the schedule.

    A free 15-day trial of the application can be downloaded through the website mentioned above.