Date Difference between MSP and P6
In the Open Standard
Ron BeecheyMember for 10 years 6 months
- Created
- 3
- 4
0
I have an activity for 22.5 days in P6 and MSP. Both have calendars that are 6X10 with Sunday non working. In P6 I get the dates 3/27/20 to 4/16/20 and in MSP 3/27/2020 to 4/24/2020.
There is a need to use the MSP plan as an overall roadmap and the detailed P6 file to feed it.
Anone have any ideas??????
Have a missed setting something in the setting in either product