SPI calculation in P6

SepSep HossMember for 14 years 6 months
Created
2
3
0
In our previous month’s update we had a forecast (remaining early)of 10 million for this month. This month our actual is much less than last month and is around 5 million. We have assigned previous month’s update as our baseline for this month. So that 10 million forecast is now our baseline. But still our SPI is 1 in P6! So even though our progress is half of our baseline our SPI is still high. Any idea what is causing this?

2 replies

Oldest first
  1. 0
    David Kelly ·

    Your talk of "actual" is

    Your talk of "actual" is confusing, SPI is a measure of Earned, not Actual. No change to Actual Hours changes SPI.

    Which baseline are you using to calculate Earned Value in the Project's "Settings"

  2. 0
    SepSep Hoss ·

    We only show revenue in our

    We only show revenue in our project. Baseline for earned value is previous month’s update which in our current month we have slipped a lot but SPI is 1!!