SPI calculation in P6
In the Open Standard
SepSep HossMember for 14 years 6 months
- Created
- 2
- 3
0
In our previous month’s update we had a forecast (remaining early)of 10 million for this month. This month our actual is much less than last month and is around 5 million. We have assigned previous month’s update as our baseline for this month. So that 10 million forecast is now our baseline. But still our SPI is 1 in P6! So even though our progress is half of our baseline our SPI is still high.
Any idea what is causing this?