Skip to content

P6 - resource is not showing activities that are completed

Mike plannerMember for 15 years 8 months
Created
2
3
0

Hello All, 

 

I suspect the resource is not showing on the activities that are completed because it is a bit light after the progress line. 

Please see image below. 

The design activities are blue resources but i cannot see anything blue on the histograme blow after that progress / data date line. 

I am suspecting the setting does not show the resources for activities that are completed but then, i can see slightly red for the construction activities which are in Red. 

I am a bit confused. 

 

Thank you for much for your help.

 

Kind regards

Mike Planner 

2 replies

Oldest first
  1. 0
    David Kelly ·

    The P6 stacked histogram

    The P6 stacked histogram shows "At Completion" hours/costs - so stage 1 of your investigation is to show that value besiide the "Budgeted" numbers you have highlighted.......

    Yes, "At Completion" is a bit bonkers....

  2. 0
    Zoltan Palffy ·

    go to view resource usage

    go to view resource usage profile and make sure that on the dat tab that you have the actua box checked. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?